Initial Review Timeframes

Subdivision Process
  1. A new application is submitted, processed, and routed within 2 days.
  2. Plans are routed to review agencies. The routing period for agency comments is 3 weeks from the date of submission of a complete application.
  3. Plans are then resubmitted and routed out to agencies to review to plan and whether agency comments have been addressed or if changes were made that may create additional comments. The routing period for agency comments is 3 weeks from the date of resubmission.
Site Plan & Preliminary Subdivisions
  1. A new application is submitted, processed and routed within 2 days.
  2. Plans are routed to review agencies. The routing period for agency comments is 3 weeks from the date of submission of a complete application.
  3. Plans are then resubmitted and routed out to agencies to review to plan and whether agency comments have been addressed or if changes were made that may create additional comments. The routing period for agency comments is 2 weeks from the date of resubmission.