Boyers Mill Road & Bridge CIP

Project Overview
To date, the Office of Transportation Engineering staff has negotiated and the Board of County Commissioners has approved several different tasks along Boyers Mill Road. Initially, the Boyers Mill Road and Bridge projects were a single Capital Improvement Project. However, the road and bridge projects were split into 2 separate Capital Improvement Projects in November 2010 due to the fact that the bridge project could move to construction quicker than the road improvement project.

For the current approved Capital Improvement Program, please visit the resource on Historical Budget Publications.

Boyers Mill Road Reconstruction
The main focus of the Boyers Mill Road improvement project is improving the safety of the road corridor from its intersection with Gas House Pike to its intersection with Old National Pike. The upgrade is needed to meet the increasing traffic demands in the area. The roadway reconstruction project will include the addition of 2 foot or 5 foot (depending on location) paved shoulders for vehicle recovery, along with horizontal and vertical geometric improvements. Stormwater management improvements will also be made along the length of the corridor. A roundabout intersection will be included in the project where Eaglehead Drive intersects with Boyers Mill Road. The addition of 8 pull-off areas to aid in speed enforcement has also been proposed.

Current Status     
A contract was awarded to a consultant for the final design of the “North section” of Boyers Mill Road from its intersection with Gas House Pike to the northern limit of the Boyers Mill Road bridge project in April 2014. The consultant delivered the 60% design at the end of October 2014. Public Meeting notices were sent out at the end of October by the Office of Transportation Engineering. Please see the “Upcoming Meetings” section below for more information.

Negotiations for the “South section” (southern limit of the Boyers Mill Road bridge project to the intersection with Old National Pike) final design are still in progress.

The design consultant will have field personnel at the project site throughout the summer months completing field surveys and other investigations. Pavement and stormwater management borings were completed October 24, 2014.  Please see the general survey notice below.
Revised 30% Design Plans
Please see links below to learn about the revised 30% design plans for the Boyers Mill Road corridor.
Roundabout Options
Traffic control at the intersection on Boyers Mill Road and Eaglehead Drive will include a roundabout. Please select from the links below for more information.

60% Design Plans
Please see links below to the 60% design plans for the Boyers Mill Road "North section".

Upcoming Meetings  
  •  None currently scheduled. 

In-the-Press 
Frederick News Post:
“’North Section’ of Boyers Mill Road Design Discussed”