Initial Review Timeframes
Initial Review Timeframes
Construction Drawings
Construction Drawings including site and subdivision improvement plans, CIP projects, revisions to approved improvement plans and reapprovals of expired improvement plans, mass grade, sediment and erosion control, road layback, common driveway, utility plans are routed with a due date of
three calendar weeks(excluding County holidays) from the date of receipt.
Note:
Second submissions are routed with a due date of
two calendar weeks(excluding County holidays) from the date of receipt; all
subsequent submissions are routed with a due date of
three calendar weeks(excluding County holidays) from the date of receipt.
Engineering Modifications, Waivers and Supporting Documents
Plans are routed with a due date of
two calendar weeks (excluding County holidays) from the date of receipt.
Engineering Field Revisions
Plans are routed with a due date of
one calendar week(excluding County holidays) from the date of receipt.