Boyers Mill Road

Project Overview


To date, the Office of Transportation Engineering staff has negotiated and the Board of County Commissioners has approved several different tasks along Boyers Mill Road. Initially, the Boyers Mill Road and Bridge projects were a single Capital Improvement Project. However, the road and bridge projects were split into 2 separate Capital Improvement Projects in November 2010 due to the fact that the bridge project could move to construction quicker than the road improvement project.

For the current approved Capital Improvement Program, please visit the resource on Historical Budget Publications.


Boyers Mill Road Reconstruction


The main focus of the Boyers Mill Road improvement project is improving the safety of the road corridor from its intersection with Gas House Pike to its intersection with Old National Pike. The upgrade is needed to meet the increasing traffic demands in the area. The roadway reconstruction project will include the addition of 2 foot or 5 foot (depending on location) paved shoulders for vehicle recovery, along with horizontal and vertical geometric improvements. Stormwater management improvements will also be made along the length of the corridor. A roundabout intersection will be included in the project where Eaglehead Drive intersects with Boyers Mill Road. The addition of multiple pull-off areas to aid in speed enforcement has also been proposed.


Current Status    

 
“North Section” Boyers Mill Road from its intersection with Gas House Pike to the northern limit of the Boyers Mill Road Bridge is currently in construction. 

Weekly Update: 

The contractor is currently working on Stage 1 preparations and Stage 1. The contractor is going to be working on utility conduit and vault installation at the Boyers Mill Road-Eaglehead Drive intersection, as well as excavation for the new alignment of Boyers Mill Road into this intersection. Work has also begun on installing the temporary road along Eaglehead Drive.  

A Public Meeting was held on April 4, 2017 at Deer Crossing Elementary School. Please see below for the general information handout and the PowerPoint presentation from the meeting.

Additional Information:
Maintenance of Traffic Narrative
Public Meeting Minutes - April 18, 2017
Public Meeting Handout - April 4, 2017
Public Meeting BMR North - slide show

“South Section” (southern limit of the Boyers Mill Road bridge project to the intersection with Old National Pike): The majority of borings have been completed.  The remainder are anticipated to be complete by the end of spring. Utility investigations have not yet been scheduled. Please contact Samantha Krautwurst if you would like to see the roadway plans.

The design consultant will continue to have field personnel at the project site completing field surveys and other investigations.   Please see the general survey notice below.

Final Design Plans - North

In-the-Press 


Frederick News Post:

“’North Section’ of Boyers Mill Road Design Discussed”

New Entrance to Villages of Nightingale
The New Entrance to the Villages of Nightingale project is a Lake Linganore Conservation Society (LLCS) project for the relocation of the Nightingale Court entrance.  Contact information: Jamie Hansen, CQA, Caliber Consulting Group, LLC  jhansen@caliber-cg.com  or 301-787-7633.