Gas House Pike Bridge

Gas House Pike Bridge Replacement


Project Overview


This federally funded Capital Improvement Program (CIP) project is for improvements to Gas House Pike at Linganore Creek for the replacement of two existing structures, a larger multi-cell structure known as Gas House Pike Bridge (Structure No. F09-21) and a nearby smaller multi-cell pipe structure just west of Gas House Pike Bridge, which will become a new bridge (Structure No. F09-25). The proposed project work will include complete removal of both existing structures, installing a single 77' span prestressed girder bridge with concrete substructure and caisson foundation, installing a single 52' span prestressed girder bridge with concrete substructure and caisson foundation, installing new bridge railings, replacing portions of the existing traffic barriers, installing new traffic barriers and end treatments, installing pipe culverts and headwall, installing storm water management facilities, installing roadway drainage improvements, installing a 10" diameter sanitary sewer line with associated items, 12" diameter water line with associated items, regrading approaches, placing full depth pavement and tying grading into existing topography. The bridge structures and roadway approaches will have two 11-foot lanes with 5-foot shoulders to meet collector standards. The CIP project will provide needed safety improvements and reduce the frequency of flooding at this location.

For the current approved Capital Improvement Program, please visit the resource on Historical Budget Publications.

Current Status


Final Design for this project is nearly complete and advertisement is anticipated for late April/early May 2019. Once the project contract has been awarded, a Notice-to-Proceed (NTP) will be determined for the start of construction. Construction start is anticipated for late summer/early fall 2019. The project requires a full-time road closure for the duration of construction and completion of the project. Project duration is estimated to be 450 calendar days. After NTP has been given, advance notification of the bridge closure will be posted at the bridge site and sent via public notification. If you have any questions regarding this project, please contact Jennifer Bohager, Project Manager, at 301-600-3505.

Contact Us

  1. Jennifer Bohager


    Project Manager, Office of Transportation
    Engineering
    Email
    Ph: 301-600-3505

    Jason M. Stitt, P.E.


    Chief, Office of Transportation Engineering
    Email
    Ph: 301-600-2932

    Address


    Frederick County Division of Public Works
    Office of Transportation Engineering
    355 Montevue  Lane, Suite 200
    Frederick, MD 21702-8213

    Hours


    Monday - Friday
    7:30 a.m. - 4 p.m.