Submittal Process and Schedule

Initial Review Timeframes


Subdivision Process

  1. A new application is submitted, processed, and routed within 2 days.
  2. Plans are routed to review agencies. The routing period for agency comments is 3 weeks from the date of initial submission of a complete application.

Site Plan & Preliminary Subdivisions

  1. A new application is submitted, processed and routed within 2 days.
  2. Plans are routed to review agencies. The routing period for agency comments is 3 weeks from the date of initial submission of a complete application.

Submittal Schedules

Submittal Schedule 2025

Submittal Schedule 2026

Subdivision and Site Plan Processes


Flow Charts

Preliminary Subdivision Plan Process

Type 1 Site Plan Process