Sidewalk Retrofit Program

Project Overview


This Capital Improvement Program (CIP) project will address deficiencies in existing pedestrian facilities within County maintained rights-of-way that were found to be non-compliant with current Americans with Disabilities Act (ADA) standards. The work includes complete reconstruction of approximately 20 miles of sidewalk and repair or replacement of 2,218 curb ramps.

Current Status


This ongoing 10-year program began in the 2015 fiscal year and is anticipated to end during the 2025 fiscal year (FY).

FY19 Replacement and Repair of Sidewalk and ADA Ramps
  • Started August 6, 2018 and is anticipated to be completed July 2019
  • Roads list
FY20 Replacement and Repair of Sidewalk and ADA Ramps
  • Anticipated to start August 2019 and is anticipated to be completed July 2020
  • Roads list